I forgot to schedule for wire lath inspection and I went ahead and applied
the stucco coats. During the final inspection, the inspection caught it and
asked that I expose a couple of spots to check the nailing and he determined
that the wire lath was under-nailed ad asked that I should fix and left open
for me. Is there any way I can increase the nailing after the fact?
thanks
a.a.



Reply from: RicodJour
Date: 07 May 2008, 14:38
Re: stucco/wire lath question

On May 6, 8:19 pm, "AA" <alaa...@bellsouth . net > wrote:
> I forgot to schedule for wire lath inspection and I went ahead and applied
> the stucco coats. During the final inspection, the inspection caught it and
> asked that I expose a couple of spots to check the nailing and he determined
> that the wire lath was under-nailed ad asked that I should fix and left open
> for me. Is there any way I can increase the nailing after the fact?
> thanks
> a.a.

Are the nails spaced too far apart? Maybe you should check out
another area to be sure. If you know the spacing doesn't cut it,
well...

Assuming that the lathing needs more nails, I think you just bought
another layer of stucco to cover the nails sufficiently. The worst
thing you could do is to not have sufficient stucco coverage over the
nails and have the stucco pop at the nail heads or have the nail heads
rust (galvanized, I know, still a risk).

R

Reply from: curt
Date: 11 May 2008, 23:20
Re: stucco/wire lath question

On Tue, 06 May 2008 20:19:39 -0400, AA wrote:

> I forgot to schedule for wire lath inspection and I went ahead and
> applied the stucco coats. During the final inspection, the inspection
> caught it and asked that I expose a couple of spots to check the nailing
> and he determined that the wire lath was under-nailed ad asked that I
> should fix and left open for me. Is there any way I can increase the
> nailing after the fact? thanks
> a.a.

I would think that it could be a challenge. You have to hit the
structure with the nails/screws and if they are studs then it will be
tough to find them under the stucco. Also, to do it properly, your
nailheads have to hit the lath and not the stucco so that the lath is
solidly attached.


Three questions I might have:
- What is the structure ? New Construction ? Plywood ? Drywall ? Is the
inside of the wall finished or open ?
- How many square feet of stucco are involved.
- When he determined that the lath is undernailed how exactly did he do
it and for what exact reason did he feel it was undernailed ?

Curt

Reply from: Glenn
Date: 12 May 2008, 00:04
Re: stucco/wire lath question

Chances are the job is fine as is.

Have you tried bribery?


"AA" <alaaali@bellsouth . net > wrote in message
news:Zz6Uj.8296$_.594@bignews8.bellsouth . net ...
>I forgot to schedule for wire lath inspection and I
>went ahead and applied the stucco coats. During the
>final inspection, the inspection caught it and asked
>that I expose a couple of spots to check the nailing
>and he determined that the wire lath was under-nailed
>ad asked that I should fix and left open for me. Is
>there any way I can increase the nailing after the
>fact?
> thanks
> a.a.
>





Login:
  Username:    Password: 
 
   Lost Password? click here!
Thread:
  curt
  Glenn